| Home | > News > Company News | 
      Unit 5 of Huaneng Nanshan Power Plant 2×460MW Gas-Steam Combined Cycle Expansion Project Completes 168-Hour Full-Load Trial Run | 
  ||
      
  | 
||
| 
     At 17:18 on March 27, 2025, Unit 5 of Huaneng Nanshan Power Plant  2×460MW Gas-Steam Combined Cycle Expansion Project constructed by SEPCO1 successfully completed 168-hour full-load trial run. At present, the unit is operating stably with optimal parameters and indicators.  | 
||
| 
     |