At 18:18 on January 28, Unit 1 of Xinyou Qitai 2 x 660MW EPC project implemented by SEPCO1 successfully completed the 168-hour full-load trial run with excellent performance indicators and good operation status. The construction of Xinyou Qitai project was restarted on March 20, 2018. Since then, all persons engaged in this project have fully and jointly adhered to the Iron Army Sprit of "dedication, innovation, and transcending", strengthening the management of Six-safety Systems, Seven-step Quality Management. Meanwhile, the project team has overcome the problems such as late availability of drawings and equipment, difficult labor organization, the tough situation of Xinjiang's social stability, extreme weather of sand storms and low temperature. They have properly coordinated the design, equipment availability, disciplines and work procedures. The company has realized eight "one-time-success" of DM water production, hydro test, turbine boxing-up, boiler light-up, turbine rolling, whole unit startup, grid connection and 168-hour trial run, which has set up a good image for SEPCO1. |